OML 26

Ogini 1ST, 27, and 28 Drilled and completed 3 wells with an average of 30days per well despite COVID19 pandemic. The average rig efficiency of 97.1% was achieved for OGINI 1ST, OGINI 27, and OGINI 28 combined as a result of this, we delivered within the planned AFE, saving our client thousands of dollars in monetary value.